Barber Grove - large diameter pipe ram

horizontal-rule

Customer:

Undisclosed

Consultant

Undisclosed

Date:

December 2022

Capability:

Mobile Plant Fleet, Pipe Ramming

Company role:

Subcontractor responsible for delivering a pipe ram.

Scope:

Installation of approximately 14m of 1200 diameter steel casing to support the installation of new wastewater infrastructure.

This was a new challenge for us, installing a large diameter casing – our largest diameter yet.

Working with a main contractor, the site team developed an excellent working relationship and the enabling works – provided by the main contractor – were of a high standard.

To install this large diameter steel casing, we used the powerful Grundoram Koloss tool to ram the casing safely and accurately into position.

We worked closely with the main contractor to help solve groundwater issues and successfully deliver the work.